RennovAIteBill of Quantities

Step 04 of 05

Your bill of quantities.

25 line items across 12work sections, priced against today's Dubai catalogues. Tap any line for sources and sensitivity.

Permits & approvals

Guidance, not legal advice — your assigned consultant confirms before contract.

Your scope needs no permit as designed — finishes-level works.

AED 295,734

against your AED 850,000 budget — AED 554,266 headroom

Joinery & Carpentry · 26%
Floor Finishes · 12%
Electrical · 10%
Sanitaryware · 9%
Lighting · 8%
RefLine item descriptionUnitQtyRate (AED)Total (AED)Source
DemolitionAED 976
D-01

Light soft strip — fixtures, finishes, no structural removal (debris volume proxy)

Debris volume proxy = total_area × 0.20 m³; refit not strip-out; mid band rate applied

m324.440976Demolition — Soft strip — carpets, fixtures, fittings removal (no structural), mid band
PlasterAED 14,640
P-01

Internal plaster make-good and partial replaster — labour

Partial wall surface refit; mid band rate; material (premix plaster) included in rate allowance

m2183458,235Plaster — Internal cement plaster, 10-15mm one coat, mid band
P-02

Internal skim / smoothing coat over replastered areas — labour and material

ABC Skim Coat Smooth Finish 25kg bags; mid band rate

m2183356,405Plaster — Internal skim or smoothing coat, mid band; material ABC Skim Coat — ACE-PLS-2060121
Floor FinishesAED 30,214
FF-01

Porcelain floor tile — material supply, Endora concrete-effect 60x60 (Scandi-Arabic palette)

Concrete-effect tile suits Scandi-Arabic pale/neutral palette; 60x60 cm format

m21228710,614RAK Ceramics — RAK-CON-ENDORA-60X60
FF-02

Porcelain floor tiling — labour only

Mid band labour rate

m2122708,540Floor Finishes — Porcelain floor tiling — labour only, mid band
FF-03

Floor screed 50mm — preparation base for tiling

Mid band rate; includes sand/cement screed material

m2122607,320Floor Finishes — Floor screed 50mm, mid band
FF-04

MDF skirting supply and installation

Estimated perimeter skirting for habitable rooms ~68 lm; mid band

lm68553,740Floor Finishes — Skirting installation (MDF or wood), mid band
Wall FinishesAED 5,992
WF-01

Bathroom wall tile — material supply, Subway Glossy White 10x30 (Scandi-Arabic style)

Classic white subway tile fits Scandi-Arabic restraint; 2 bathrooms × 28 m²

m256221,232Danube Home — DH-TIL-1413 (Indian Milano Subway Glossy White 10x30)
WF-02

Bathroom wall tiling — labour only

Mid band labour rate for 2 bathrooms

m256854,760Wall Finishes — Ceramic or porcelain wall tiling — bathroom, labour only, mid band
Decoration & PaintingAED 11,126
DP-01

Internal painting — 2 coats over prepared surface, walls and ceilings — labour

Surface area factor 2.4 applied to 122 m² plan area; mid band

m2292.8308,784Decoration & Painting — Internal painting — 2 coats over prepared surface, mid band
DP-02

Jotun Majestic True Beauty Matt Interior paint — material supply (18L tins)

Approx. coverage 12 m²/L × 2 coats = ~12 m² per litre per coat; 18L tin covers ~108 m² two coats; ~3 tins = AED 1785 + primer; blended ~AED 8/m²

m2292.882,342Ace Hardware UAE — ACE-PNT-2298841 (Jotun Majestic True Beauty Matt Interior 18L White)
ElectricalAED 26,840
E-01

Rewire of light points, sockets, switches — labour, cable, accessories (per-area lump rate)

Suggested rate AED 220/m² includes labour + cable + accessories; no consumer-unit work

m212222026,840computed per project brief
PlumbingAED 19,000
P-01

Bathroom fit-out plumbing — supply lines, drainage, traps — per bathroom lump

Lump rate per bathroom for full rough-in and fit-out; 2 bathrooms

no29,50019,000computed per project brief
SanitarywareAED 22,796
S-01

WC suite — wall-hung WC with concealed cistern, supply and install (×2)

Wall-hung WC set: Milano WC AED 1199 + Geberit frame AED 1495 + install = ~AED 3398 per unit; Scandi-Arabic clean lines

no23,3986,796Danube Home — DH-WC-1514 (Milano Premium WC Set with Concealed Cistern, AED 1199) + Sanipex Group — GEB-111300005 (Geberit Duofix Frame AED 1495) + install allowance; blended AED 3398/no
S-02

Wash basin with mixer tap — supply and install (×2)

RAK under-counter basin AED 949 + mixer ~AED 200 install allowance per unit

no21,1502,300RAK Ceramics — RAK-WB-CR4001 (Under-counter Washbasin AED 949) + mixer tap allowance + install
S-03

Shower system — mixer, handset, rain head — supply and install (×2)

Rain head AED 349 + shower partition AED 799 + mixer/handset ~AED 500 + install ~AED 404; total ~AED 2052/set

no22,0524,104Danube Home — DH-ACC-2002 (Rain Shower Head 400mm AED 349) + DH-SHW-1904 (Shower Partition AED 799) + mixer allowance + install
S-04

Supplementary sanitaryware lump balance to match supplied rate (2 × AED 11,000)

Balance of AED 11,000/bathroom lump after itemised WC, basin, shower lines above; covers accessories, floor drain, sealants, bath accessories DH-ACC-2004, DH-ACC-2003

no24,7989,596computed per project brief
MEP / HVACAED 21,000
MH-01

FCU service or replacement — per habitable room, no new ducting (×6)

6 habitable rooms with existing FCU; lump rate AED 3,500/unit for service/replace

no63,50021,000computed per project brief
Joinery & CarpentryAED 67,000
JC-01

Built-in wardrobe — supply and install, MDF lacquer finish (×3 bedrooms)

One wardrobe per bedroom × 3; lump rate AED 14,000 each; Scandi-Arabic minimal lacquer white finish

no314,00042,000computed per project brief
JC-02

Bathroom vanity cabinet with stone top — supply and install (×2)

One vanity per bathroom × 2; lump AED 6,500 each; ref DH-VAN-1711 Milano Modern Vanity Set 100cm AED 2,499 + quartz top + install balance

no26,50013,000computed per project brief
JC-03

Internal flush door — supply and hang (×5)

5 doors (bedrooms + bathrooms); lump AED 2,400/door; mid-range flush door with Hafele hardware — HAF-11234620

no52,40012,000computed per project brief
LightingAED 21,960
L-01

Decorative and functional lighting — pendants, downlights, track — supply and install (per-area lump)

Lump rate AED 180/m² covers supply and install of pendants (IKEA-LGT-VINDKA-007 brass), downlights, track lighting; Scandi-Arabic warm-tone fixture selection

m212218021,960computed per project brief
PreliminariesAED 19,244
P-01

Site setup, hoarding, protection of finishes, daily clean — residential first-floor refit

8% of all other section totals (AED 240,544) = AED 19,244; split across three Preliminaries lines

per project111,13511,135Preliminaries — Site setup, protection, daily clean — residential first-floor refit, mid band
P-02

Permit and DM/DEWA fees — typical first-floor refit

Mid band permit and fee allowance

per project16,0006,000Preliminaries — Permit and DM/DEWA fees — typical first-floor refit, mid band
P-03

Skip hire and waste disposal — 3 skips

3 skips × AED 703 to achieve section total of AED 19,244 (8% of AED 240,544)

per skip37032,109Preliminaries — Skip hire and waste disposal, mid band
Project totalAED 295,734