RennovAIteBill of Quantities

Step 04 of 05

Your bill of quantities.

56 line items across 17work sections, priced against today's Dubai catalogues. Tap any line for sources and sensitivity.

Permits & approvals

Guidance, not legal advice — your assigned consultant confirms before contract.

Your scope needs no permit as designed — finishes-level works.

AED 594,273

against your AED 850,000 budget — AED 255,727 headroom

Aluminum & Glass · 20%
Joinery · 14%
Demolition · 11%
Floor Finishes · 10%
Plaster · 7%
RefLine item descriptionUnitQtyRate (AED)Total (AED)Source
DemolitionAED 50,031
D-01

Wall demolition + cart away

Aggregated from 52 element take-off items.

m2555.99050,031Deterministic take-off (P4)
BlockworkAED 15,000
B-01

Civil alterations — opening closures/openings, new partitions, storage room

R-35: Civil alterations allowance — door-opening closures/openings, new partition walls, storage-room blockwork (Villa 94 §2: AED 15k). Design-dependent; QS to re-measure per project.; allowance pending design layout (R-35)

project115,00015,000allowance
PlasterAED 30,575
P-01

Wall plaster / skim coat (net of openings)

Aggregated from 52 element take-off items.

m2555.95530,575Deterministic take-off (P4)
Floor FinishesAED 44,470
FF-01

Floor finish — supply & install

Aggregated from 12 element take-off items.

m2152.819029,032Deterministic take-off (P4)
FF-02

Staircase tile — developed tread/riser surface (144×305 slab)

R-44: RAK Surface XL 144×305 slab, list rate — staircase; developed area × C-08 factor; QS to confirm from stair drawing; F-16: stair footprint 13.3 m² × 2.6 (C-08) = 34.58 m²

m234.58446.4515,438allowance
Wall FinishesAED 25,100
WF-01

Wet-area wall tiling — supply & install

Aggregated from 3 element take-off items.

m296.5426025,100Deterministic take-off (P4)
CeilingsAED 21,593
C-01

Gypsum ceiling + finish

Aggregated from 13 element take-off items.

m2166.113021,593Deterministic take-off (P4)
SanitarywareAED 14,910
S-01

Wall-hung WC incl. concealed cistern — install

R-19: low band (tier value); 1 per bathroom × 3

no31,4004,200labour_rates: WC suite supply and install — mid-range
S-02

Vanity basin with mixer — install

R-20: low band (tier value); 1 per bathroom × 3

no39002,700labour_rates: Wash basin with mixer — supply and install
S-03

Shower system with concealed thermostatic valve — install

R-21: low band (tier value); 1 per bathroom × 3

no31,5004,500labour_rates: Shower system — mixer, handset, rain head
S-04

Shattaf (health faucet), matt black — supply

R-40: GROHE shattaf, matt black — Laspinas 46703 line 1025302431 (supply); 1 per wet room × 3 (Laspinas)

no3250750allowance
S-05

Paper holder, matt black — supply

R-41: GROHE Essentials paper holder, matt black — Laspinas 46703 line 1024652430; 1 per wet room × 3 (Laspinas)

no3210630allowance
S-06

Towel rail, matt black — supply

R-42: GROHE Essentials towel rail, matt black — Laspinas 46703 line 1022512430; 1 per wet room × 3 (Laspinas)

no3260780allowance
S-07

WC actuator plate, vertical square — supply

R-43: GROHE actuator plate, vertical square — Laspinas 46703 line 38732KF0; 1 per wet room × 3 (Laspinas)

no34501,350allowance
ElectricalAED 9,620
E-01

LED downlights — supply and install (interior)

R-14: low band (tier value); F-06: Σ interior ceil(area / 3.5) = 40

no401104,400labour_rates: LED downlight — supply and install
E-02

Power sockets and switches — supply and install (interior)

R-15: low band (tier value); F-07: Σ interior ceil(area × 0.4) = 58

no58905,220labour_rates: Power socket or switch — supply and install
PlumbingAED 19,050
P-01

Bathroom plumbing re-pipe (full PPR) — per bathroom

R-16: low band (tier value); bathroom count = 3

no34,50013,500labour_rates: Bathroom plumbing rewire — per bathroom, full
P-02

Concealed water heater — supply and install

R-17: low band (tier value); 1 per bathroom × 3 (Villa 94 retained existing heaters — QS to confirm inclusion)

no31,5004,500labour_rates: Concealed water heater — supply and install
P-03

Floor / linear shower drain — install

R-18: low band (tier value); 1 per bathroom × 3

no33501,050labour_rates: Floor drain — supply and install
MEP / HVACAED 16,400
MH-01

New ducted AC unit incl. ductwork, grilles, thermostat — secondary bedrooms

R-32: low band (tier value); F-15: 1 per secondary bedroom × 2

no28,00016,000labour_rates: Concealed ducted AC FCU replacement
MH-02

FCU deep service and clean — retained units

R-22: low band (tier value); rooms retaining existing FCU = 2

no2200400labour_rates: AC servicing and cleaning
LightingAED 750
L-01

Decorative pendants — installation

R-26: low band (tier value); F-09: 1 per bedroom (3) + 2 living = 5

no5150750labour_rates: Decorative pendant — installation labour only
Decoration & PaintingAED 19,457
DP-01

Wall painting — primer + 2 coats

Aggregated from 52 element take-off items.

m2555.93519,457Deterministic take-off (P4)
PreliminariesAED 20,229
P-01

Site setup, hoarding, protection, daily clean

R-27: low band (tier value); lump sum per project

project16,0006,000labour_rates: Site setup, protection, daily clean — residential first-floor refit
P-02

DM / DEWA permits and fees

R-28: low band (tier value); lump sum per project

project12,5002,500labour_rates: Permit and DM/DEWA fees — typical first-floor refit
P-03

Skip hire and waste disposal

R-29: low band (tier value); F-11: ceil(166.1 × 0.2 ÷ 4.5) = 8 skips

no88006,400labour_rates: Skip hire and waste disposal
P-04

Protective floor covering over new tiling until handover

R-37: Protective floor covering over new tiling until handover, AED 8/m². QS to confirm.; F-14: total floor area = 166.1 m²

m2166.181,329allowance
P-05

Rolling scaffold hire — ceiling + painting works

R-38: Rolling scaffold hire for ceiling + painting works, lump. QS to confirm.; lump sum per project

project12,5002,500allowance
P-06

Final clearance + professional handover clean

R-39: Final site clearance + professional handover clean, lump. QS to confirm.; lump sum per project

project11,5001,500allowance
Electrical InstallationsAED 8,380
EI-01

13A twin switched socket outlet — supply & install

Count from 2D socket_13a fixtures on the plan.

no221202,640Overlay point rate (P2 default)
EI-02

1-gang lighting switch — supply & install

Count from 2D switch_1g fixtures on the plan.

no990810Overlay point rate (P2 default)
EI-03

2-way lighting switch — supply & install

Count from 2D switch_2way fixtures on the plan.

no101301,300Overlay point rate (P2 default)
EI-04

Ceiling light point — wiring + fitting allowance

Count from 2D light_point fixtures on the plan.

no171101,870Overlay point rate (P2 default)
EI-05

Split-AC indoor unit power + control point

Count from 2D ac_point fixtures on the plan.

no43501,400Overlay point rate (P2 default)
EI-06

Double-pole isolator switch — supply & install

Count from 2D dp_isolator fixtures on the plan.

no2180360Overlay point rate (P2 default)
EI-07

Structured-cabling data/TV outlet — supply & install

Count from 2D data_point fixtures on the plan.

no100TBC — QS to price
Plumbing & SanitaryAED 6,440
PS-01

WC supply + soil connection — first & second fix

Count from 2D wc_point fixtures on the plan.

no38502,550Overlay point rate (P2 default)
PS-02

Wash-basin supply + waste — first & second fix

Count from 2D basin_point fixtures on the plan.

no36501,950Overlay point rate (P2 default)
PS-03

Shower mixer supply point — first & second fix

Count from 2D shower_mixer fixtures on the plan.

no27501,500Overlay point rate (P2 default)
PS-04

Electric water heater — supply & install

Count from 2D water_heater fixtures on the plan.

no200TBC — QS to price
PS-05

Wet-area floor drain + trap — supply & install

Count from 2D floor_drain fixtures on the plan.

no2220440Overlay point rate (P2 default)
JoineryAED 66,016
J-01

Master bedroom dresser cabinet, glass doors + LED

Heuristic: 10.08 m² per master (Atrium 1.1)

m210.081,10011,088Atrium Technical Services QTN20261407 (actual composite rates)
J-02

Master bedroom wall cladding with hidden LED

Heuristic: 6.16 m² per master (Atrium 1.2)

m26.168004,928Atrium Technical Services QTN20261407 (actual composite rates)
J-03

Fitted bedroom cabinet, melamine MDF + architrave

Heuristic: 7 m² per bedroom × 2 (Atrium 2.1/3.1)

m21485011,900Atrium Technical Services QTN20261407 (actual composite rates)
J-04

Bathroom cabinet with doors, MR melamine

One per bathroom × 3

item32,4007,200Atrium Technical Services QTN20261407 (actual composite rates)
J-05

Bathroom vanity box, MR melamine

One per bathroom × 3

item31,8005,400Atrium Technical Services QTN20261407 (actual composite rates)
J-06

Solid door leaf, new handle + hinges

Bedrooms + bathrooms = 6 leaves (Atrium 5.1)

no62,70016,200Atrium Technical Services QTN20261407 (actual composite rates)
J-07

Solid meranti door frame, painted + fixed

6 frames (Atrium 5.2)

no61,5509,300Atrium Technical Services QTN20261407 (actual composite rates)
Aluminum & GlassAED 92,449
AG-01

Guest bedroom — Thermal-break hinged door + curved fixed DG glass, 700×2650

Requires site measurement — allowance only

no25,15010,300Global Creation Services ref 3936/R1 (allowance)
AG-02

Master bedroom — Thermal-break hinged door + curved fixed DG glass, 700×2650

Requires site measurement — allowance only

no25,15010,300Global Creation Services ref 3936/R1 (allowance)
AG-03

Master bathroom — Tilt & turn system DG, 950×950

Requires site measurement — allowance only

no13,0003,000Global Creation Services ref 3936/R1 (allowance)
AG-04

Kids bedroom — Thermal-break sliding system DG, 1850×2460

Requires site measurement — allowance only

no112,04012,040Global Creation Services ref 3936/R1 (allowance)
AG-05

Office — Thermal-break sliding system DG, 1700×2300

Requires site measurement — allowance only

no110,38410,384Global Creation Services ref 3936/R1 (allowance)
AG-06

Office — Thermal-break sliding system DG, 1830×3000

Requires site measurement — allowance only

no114,17614,176Global Creation Services ref 3936/R1 (allowance)
AG-07

Living area — Skylight DG, 1830×3750

Requires site measurement — allowance only

no115,74915,749Global Creation Services ref 3936/R1 (allowance)
AG-08

G.F–F.F stair — Shaped glass balustrade 12mm tinted bronze

Requires site measurement — allowance only

lm101,65016,500Global Creation Services ref 3936/R1 (allowance)
Project totalAED 594,273
Optional — not in contractor scopeFurniture (optional)Indicative Dubai retail — furnishing your staged renders. Excluded from the contractor package.
AED 5,580
Master Bedroom — smoked-oak platform king bed12,6002,600IKEA (indicative)
Master Bedroom — floating stone-top bedsides (pair)1500500IKEA (indicative)
Master Bedroom — graphite leather bench1550550IKEA (indicative)
Master Bedroom — smoked-oak dresser, push-to-open11,2001,200IKEA (indicative)
Master Bedroom — wool rug 200×3001550550IKEA (indicative)
Master Bedroom — alabaster bedside lamps (pair)1180180IKEA (indicative)